Wakanda News Details

Judge: 'Back-door agreement' of conspiracy between EMBD, contractor - Trinidad and Tobago Newsday

La Brea-based mega contractor Namalco will receive considerably less than the $1.3 billion it was claiming from the Estate Management Business Development Company (EMBD) for contracts to develop plots for ex-Caroni (1975) Ltd workers.

Namalco's demand for payment was for six projects, but only four were dealt with by Justice Ricky Rahim in his 245 page-decision decision on Tuesday - Cedar Hill, Roopsingh Road, Petit Morne, and Picton Monkey Town.

In his ruling, the judge ordered the payment of damages to Namalco for breach of contract but voided several supplementary agreements between the state company and Namalco to the tune of millions because of 'acts of unlawful means conspiracy.'

Namalco stands to receive over $427.5 million for three of the contracts, while the fourth is to be assessed based on work done.

In invalidating the supplementary agreements, Rahim found inferences of a 'back-door agreement' between the ex-EMBD chief executive officer Seebalack Singh and Namalco to pay higher prices.

At the trial, EMBD accepted it could offer no direct evidence of a conspiracy, but the court held it could be inferred that a combination of actions 'were committed with only one intention. Put simply, to extract more money from the state entity EMBD than Namalco would have been entitled to.

Rahim added, 'This issue has been scrutinised by this court and has caused much disquiet as there appears, on the evidence, to be a lurking suspicion of agreement.'

It was also found that the tendering rules were contravened and the tendering process was not adhered to in relation to the supplementary agreements.

The case before Rahim began in 2019 and over 450,000 pages of evidence were presented to the court in what was considered one of the largest civil trials.

Namalco claimed the contracts provided for it to carry out and complete works to the design specification of EMBD and/or its engineer.

Those works were to be evaluated by the engineer, with payment being made from time to time upon the issue of certificates called interim payment certificates (IPCs).

Namalco claims that under the FIDIC conditions, EMBD was obligated to pay the amount certified in each IPC within a specified number of days after receipt of certain stipulated documentation.

Namalco also claimed the EMBD breached its own policies on the handling of the contracts.

In turn, EMBD brought claims against four ancillary defendants seeking indemnity or contribution should the court find it liable to Namalco. Those defendants were Andrew Walker, Atlantic Project Consultants Ltd, BBFL Civil Ltd, and Lee Young and Partners.

In its defence and counterclaim, EMBD contended that the sums certified in relation to the contracts were not binding; invoices were inflated, and fees were reduced to take into account deficiencies in the quality of the work.

On the counterclaim, Rahim held while there were some breaches of duty by the engineers, since EMBD suffered no loss, its claim for indemnity was dismissed.

The ancillary claim against Wa

You may also like

More from Home - Trinidad and Tobago Newsday

Science Facts

Arts Facts